New Zip-Clip Project Case Study

Back to Blog Listing

New Zip-Clip Project Case Study

BARNSLEY SCHOOLS PROJECTS UTILISING ZIP-CLIP PLUS-ON-WIRE SYSTEM

Steel Wire Cable Tray Fabrication Guide

BARNSLEY SCHOOLS PROJECTS UTILISING ZIP-CLIP PLUS-ON-WIRE SYSTEM

In 2009 a new wave of projects began in Barnsley under the Building Schools for the Future (BSF) government investment programme. The projects covered the following schools: Pennistone Grammar*, Carlton School, Kirkbalk School, Denton School, Shafton School and Springwell School

Crown House Technologies (CHT) undertook mechanical and electrical installations on all of the projects and utilised Zip-Clip’s innovative heavy-duty support systems to hang the modular containment on each of the schools.

Suspension from Concrete Ceiling 

• Suspension wires were secured to the concrete ceilings using Zip-Clip

Con-Lock hammer-set fixings prior to module installation.

• Zip-Clip locking clips were placed on wires ready to be installed into channel.

• Each support offered a Safe Working Load of 90kg with safety factor of 5:1.


Pipe Work Module Installation 

• The Zip-Clip Plus-on-Wire system was used to support pipe work modules.

• Wires were fixed using M8 eye-bolts into uni-strut with a channel nut.

• Wire was passed through slots of the strut at the bottom of the support.

• A locking clip was fed up each wire behind the strut to form a fix.

• Modules were raised into position and locking clips were fixed into place,

allowing for easy adjustment if required

Cable Basket Module Installation 

• Suspension wires were secured using M8 eye-bolts into Unistrut.

• Locking clips were secured into the profile of the channel.

• Wires were passed through the locking clips to secure modules in place


Suspension from Ceiling Fixed Channel 

• Wire drops were fixed to ceiling using M8 eye-bolts into channel.

• Locking clips were secured into the profile of the channel.

• Wire was finally pushed through the locking clips and the containment was secured at the desired height.

DP Building Systems and Zip-Clip are available to provide wire suspension expertise from initial

concept and planning through to installation and compliance sign-off.